§ 1109. System maintenance.  


Latest version.
  • (a)

    It shall be the responsibility of the developer to maintain all facilities required by the stormwater management plan during construction and for a two-year maintenance period following approval of the final subdivision plat or issuance of a certificate of occupancy, as applicable. The developer shall be responsible for removing temporary structures or facilities at the completion of the construction.

    (b)

    The owner of the property shall be responsible for maintaining the permanent stormwater management facilities identified by the stormwater management plan to remain after construction is complete, following the two-year maintenance period.

    (c)

    Should an owner or developer, whichever is the responsible party, fail to maintain the stormwater management facilities in a state of service intended by the stormwater management plan, then the public development department shall notify the responsible party in writing of the deficiencies and specific minimum maintenance requirements to remedy such deficiencies.

    (d)

    If the responsible party fails to perform the required maintenance work within a reasonable period of time (30 days maximum), then the owner shall be in violation of the provisions of this UDC.

    1110.png

(Ord. No. 17-003 , § 1, 10-2-2017)