§ 1148. Responsibilities after permit issuance.  


Latest version.
  • Upon issuance of the permit, the applicant or other responsible party conducting the land development project shall be subject to the following requirements:

    (a)

    The applicant shall comply with all applicable requirements of the approved plan and this article and shall certify that all land clearing, construction, land development and drainage will be performed according to the approved plan;

    (b)

    The land development project shall be conducted only within the area specified in the approved plan;

    (c)

    County personnel shall have access to the site to conduct periodic inspections of the project;

    (d)

    No changes shall be made to an approved plan without review and written approval by the director of public development; and

    (e)

    Upon completion of the project, the applicant or other responsible party shall submit the engineer's report and certificate and as-built plans required by this article.

(Ord. No. 17-003 , § 1, 10-2-2017)