§ 1361. Planning commission recommendation.  


Latest version.
  • (a)

    Time frame for recommendation. Within 32 calendar days of the date of the public hearing held by the planning commission on the application, the planning commission shall provide a recommendation on all applications for special use or elect to make no recommendation. This time limit may be extended if the applicant consents to extend the time frame. In the event a special use application triggers a development of regional impact (DRI) review, the time frame shall be extended to accommodate the DRI review process.

    (b)

    Recommendation. The planning commission may recommend approval or disapproval of the proposed special use applied for, may recommend conditions of approval, or it may elect to provide no recommendation. The planning commission may also recommend a reduction of the boundaries of the area devoted to the special use that is less than that requested by the applicant.

    (c)

    Consideration of information. In rendering a recommendation on any such application, the planning commission shall consider information supplied by the applicant and any report and/or recommendation from the public development department.

(Ord. No. 17-003 , § 1, 10-2-2017)