§ 2059. Gas.  


Latest version.
  • (a)

    Rough piping inspection: To be made after all new piping authorized by the permit has been installed, and before any such piping has been covered or concealed or any fixtures or gas appliances have been connected.

    (b)

    Final piping inspection: To be made after all piping authorized by the permit has been installed and after all portions which are to be concealed by plastering or otherwise have been so concealed, and before any fixtures or gas appliances have been connected. This inspection shall include a pressure test.

    (c)

    Final inspection: To be made on all new gas work authorized by the permit and such portions of existing systems as may be affected by new work or any changes in order to insure compliance with all the requirements of the construction codes and to assure that the installation and construction of the gas system is in accordance with reviewed plans.

(Ord. No. 17-003 , § 1, 10-2-2017)