§ 2060. Energy.  


Latest version.
  • (a)

    Foundation inspection: To be made before slab concrete is poured in place. To verify that perimeter insulation has been installed correctly on any slab on grade foundations, if required.

    (b)

    Frame inspection: To be made before exterior wall insulation is concealed by wall board to check installation of exterior walls insulation and to inspect that all holes and cracks through the structure envelope have been sealed in an appropriate manner as to restrict air passage.

    (c)

    Final inspection: To be made after the building is completed and ready for occupancy, to verify installation and R-value of ceiling and floor insulation, to verify correct SEER ratings on appliances, and to verify the building envelope tightness has been demonstrated and documented on the Georgia Residential Energy Code Compliance Checklist.

(Ord. No. 17-003 , § 1, 10-2-2017)