§ 3-037. Construction field office, temporary.  


Latest version.
  • Industrialized or other temporary buildings or structures may be used for a temporary construction field office, subject to compliance with the following regulations:

    (a)

    Approval and permit. Approval by the public development director and issuance of a permit by the building inspector shall be required. Said permit shall be temporary but renewable once after a period of six months.

    (b)

    Development approval. A construction field office shall not be erected or established until plans and permit(s) have been approved for one or more permanent buildings on the subject property.

    (c)

    Water and sewer. Adequate water and sewage disposal for the structure(s) shall be approved by the Jackson County Environmental Health Department.

    (d)

    Removal. Said industrialized or temporary building or structure(s) shall be removed from the site no later than upon the occupancy of the appropriate permanent building(s) or structure(s) intended for such use.

(Ord. No. 17-003 , § 1, 10-2-2017)