§ 825. District action on land disturbance permit application.  


Latest version.
  • (a)

    Upon receipt of a completed application and plans for a land-disturbance permit, the department of public development (local issuing authority) shall refer the application and plan to the district for its review and approval or disapproval concerning the adequacy of the erosion, sedimentation and pollution control plan.

    (b)

    The district shall approve or disapprove a plan within 35 days of receipt. Failure of the district to act within 35 days shall be considered an approval of the pending plan. The results of the district review shall be forwarded to the department of public development. No land disturbance permit will be issued unless the plan has been approved by the district, all fees have been paid, financial surety has been obtained, and any variances required have has been obtained.

(Ord. No. 17-003 , § 1, 10-2-2017)