§ 908. Permit commencement, expiration and extension.  


Latest version.
  • (a)

    Each permit issued by the department of public development shall have a set commencement and expiration date based on information provided in the applicant's permit application. When the construction under any permit is completed, the utility shall notify the department of public development. The permit shall remain in place until construction or activity authorized under the permit is completed or until its expiration date unless the utility is in default.

    (b)

    If work is not begun within six months of the date of permit issuance, the permit will automatically expire.

    (c)

    The director of public development is authorized but shall not be obligated to grant an extension to a permit prior to expiration, upon application, and provided that a permit review fee required for a permit application is paid.

(Ord. No. 17-003 , § 1, 10-2-2017)