§ 910. Termination of permit.  


Latest version.
  • If a utility fails to cure a default within 20 calendar days after such notice is provided to the utility by the county, then such default shall be a material breach and the county may exercise any remedies or rights it has at law or in equity to terminate the permit. If the director of public development decides there is cause or reason to terminate, the following procedure shall be followed:

    (a)

    The director or designee shall serve a utility with a written notice of the reason or cause for proposed termination and shall allow a utility a minimum of 15 calendar days to cure its breach; and

    (b)

    If the utility fails to cure within 15 calendar days, the county may declare the permit terminated.

(Ord. No. 17-003 , § 1, 10-2-2017)