§ 2055. Building.  


Latest version.
  • (a)

    Foundation and foundation wall inspection: To be made after trenches are excavated, the reinforcement is in place, and the forms erected, prior to the placing of concrete.

    (b)

    Slab inspection: To be made prior to the placing of concrete.

    (c)

    Frame inspection: To be made after the roof, all framing, fireblocking, bracing and fasteners are in place, all concealed wiring, all pipes, chimneys, ducts, and vents are complete.

    (d)

    Moisture barrier inspection: To be made prior to the installation of the exterior finishing materials.

    (e)

    Final inspection: To be made after the building is completed and ready for immediate occupancy.

(Ord. No. 17-003 , § 1, 10-2-2017)