(a)
Underground inspection: To be made after trenches or ditches are excavated, conduit or cable installed, and before any backfill is put in place.
(b)
Rough-in inspection: To be made after the roof, framing, fireblocking, and bracing is in place and prior to the installation of wall or ceiling membranes.
(c)
Final inspection: To be made after the building is complete, all required electrical fixtures are in place and properly connected or protected, and the structure is ready for occupancy.